As a consultant, I have to perform my work based on my clients previous decisions, no matter what instrument they have chosen or project they have been tasked to perform. While I dont mind earning money, very, very often, it takes a lot longer than anticipated to move a PAT project to the validation and implementation stage because the client tried to save money at the outset of the project.As a way of explaining, allow me to discuss some costs in any business, but pharmaceuticals, in particular. A few years ago, I noticed a poster in the lunchroom of the company where I was working. The question posed was, What is your salary? It went on to discuss the amount of social security taxes the company paid, its donations to our 401K, health insurance benefits, educational benefits, and so forth. The actual salary amounted to nearly twice our stated yearly compensation. Then, I remembered my director suggesting that I put my departments glassware or chemical orders on one purchase order, because it cost $35 to type each one.This got me to thinking about what a scientist, secretary, director or any employee actually costs a company. To make it simple, I assumed an average salary for everyone (dont you wish?). Then, I took into account the cost of raw materials, electricity, fuel oil, depreciation on lab and process equipment, rent and/or property taxes, income taxes, maintenance of the property and buildings, other insurances, salaries, travel costs, lunches for meetings, professional training, company cars, and all the other outlays of money throughout the year. At that time, a conservative estimate would have been a cost of $200-300/hour for every person in the company.
If you base the purchase of any instrument on cost, and the project takes longer or, worse yet, fails because the instrument is inadequate, you could easily waste $1,000,000. Photo courtesy of Dichroma.com.
In light of a PAT or even a simple analytical method development project, that hourly figure takes on new meaning. Under the old paradigm of analytical method development, the cost of instrument we purchased, for example an HPLC, was assumed to be amortized over numerous projects. In order to keep within a (compartmentalized) budget, the best price was considered before ordering. When you add the 15th or 20th LC to your lab, the true costs of development are blurred.However, when you begin a stand-alone PAT program, costs are amplified in the eyes of managers, who often assume that the first PAT project will be a single-bullet type. That is, we choose a process and proceed to optimize it. The analytical instrument, e.g., a NIR spectrometer, will be used (it is assumed) for this one job. We proceed to apply the lab-based paradigm of cost effectiveness and look for a bargain. This is the penny-wise approach. What we do not account for in this price are the other costs. I will use as for an example a project I worked on to assay tablets via NIR transmission. After we purchased the analyzer for X dollars, we began the project.The lab team consisted of a group leader, a lead chemist, and a second chemist, and an outside consultant (not me). After a month or so, the team decided that it needed specialty tablets of a larger range; this involved two people from Product Development and their equipment. We needed to analyze the tablets using a reference HPLC method. This involved the second chemist and another chemist from a second group (with his robotic system). As the work proceeded, we involved the Quality Assurance department with the validation report; an investigator and a technical writer were also assigned to the project.But that doesnt count the input from the Information Technology group and the time spent helping with our software validation. The assistance from the instrument company was gratis. Our director didnt work for free, either; he needed to oversee all our progress. Had we been doing an actual at-line or on-line method, Production personnel would have been involved along with people from the engineering department. Of course, the purchasing department was a big help, too. So, the project took well over a year from concept to final approval from QA and Management.Now, lets look at the true cost of developing a simple NIR assay method. Since we all worked on other projects and put out fires throughout the year, we cannot count 100% of the time, but I did some conservative costing for the people involved. The total number of people who touched the ball included:
In light of a PAT or even a simple analytical method development project, that hourly figure takes on new meaning. Under the old paradigm of analytical method development, the cost of instrument we purchased, for example an HPLC, was assumed to be amortized over numerous projects. In order to keep within a (compartmentalized) budget, the best price was considered before ordering. When you add the 15th or 20th LC to your lab, the true costs of development are blurred.However, when you begin a stand-alone PAT program, costs are amplified in the eyes of managers, who often assume that the first PAT project will be a single-bullet type. That is, we choose a process and proceed to optimize it. The analytical instrument, e.g., a NIR spectrometer, will be used (it is assumed) for this one job. We proceed to apply the lab-based paradigm of cost effectiveness and look for a bargain. This is the penny-wise approach. What we do not account for in this price are the other costs. I will use as for an example a project I worked on to assay tablets via NIR transmission. After we purchased the analyzer for X dollars, we began the project.The lab team consisted of a group leader, a lead chemist, and a second chemist, and an outside consultant (not me). After a month or so, the team decided that it needed specialty tablets of a larger range; this involved two people from Product Development and their equipment. We needed to analyze the tablets using a reference HPLC method. This involved the second chemist and another chemist from a second group (with his robotic system). As the work proceeded, we involved the Quality Assurance department with the validation report; an investigator and a technical writer were also assigned to the project.But that doesnt count the input from the Information Technology group and the time spent helping with our software validation. The assistance from the instrument company was gratis. Our director didnt work for free, either; he needed to oversee all our progress. Had we been doing an actual at-line or on-line method, Production personnel would have been involved along with people from the engineering department. Of course, the purchasing department was a big help, too. So, the project took well over a year from concept to final approval from QA and Management.Now, lets look at the true cost of developing a simple NIR assay method. Since we all worked on other projects and put out fires throughout the year, we cannot count 100% of the time, but I did some conservative costing for the people involved. The total number of people who touched the ball included:
- Three from the Methods Group
- Two from Product Development
- Two from Quality Assurance
- One from Analytical
- One from Information Technology
- One manager
- One consultant
- One from Purchasing
- Freebies from the instrument company